Others
300,000 DWT (General Cargo)
Period :
14 days
Place :
Korea
Completion :
2022.07.14
Vessel Details
Year of Built 2011 Class KR Flag Marshall Islands
Specification for Scrubber
Main Engine
  • CR : 15,820 kW
  • Design load for Scrubber : 60% (9,492 kW)
  • Gas flow at design load : 76,167 kg/h
Auxiliary Engine
  • CR : 1,060 kW
  • Design load for Scrubber : 75% (795 kW)
  • Gas flow at design load : 7,394 kg/h
Boiler
  • esign load for Scrubber : N/A
  • Gas flow at design load : N/A
Scrubber
  • onnection to Scrubber tower : M/E + 3 set A/E
  • Operating condition for design : M/E + 2 set A/E
  • Total Gas : 90,955 kg/h
Time Table
Vessel berthed at Miboo shipyard (Gwangyang)
  • 30 June 2022
Work Start
  • 30 June 2022
Work Complete (Including seatrial)
  • 14 July 2022