Container
6,574 TEU
Period :
14 days
Place :
Korea
Completion :
2021.12.17
Vessel Details
Year of Built 2010 Class KR Flag Korea(Jeju)
Specification for Scrubber
Main Engine
  • CR : 57,100kW
  • Design load for Scrubber : 50% (28,550kW)
  • Gas flow at design load : 288,500kg/h
Auxiliary Engine
  • CR : 2,210kW
  • Design load for Scrubber : 80% (1,768kW)
  • Gas flow at design load : 12,631kg/h
Boiler
  • esign load for Scrubber : N/A
  • Gas flow at design load : N/A
Scrubber
  • onnection to Scrubber tower : M/E + 4 set A/E
  • Operating condition for design : M/E + 2 set A/E
  • Total Gas : 313,762kg/h
Time Table
Vessel berthed at Hanla IMS yard (Gwangyang)
  • 04 December 2021
Work Start
  • 04 December 2021
Work Complete (Including seatrial)
  • 17 December 2021